First-piece inspection (FPI)

First-piece inspection is the check made on the first part after a setup, tool change or program change — the batch only runs once that part is approved.

Updated November 20263 min read

← All glossary terms

On a CNC floor, the first part after a setup is a test. Until it is measured and approved, every part made after it is a gamble — so the machine waits.

When it happens

First-piece inspection is triggered by anything that could change the part:

  • A new setup or changeover to a different part
  • A tool change on a critical feature, or new inserts
  • A program edit or offset correction
  • The start of a shift, in many plants, even with no change

What gets checked

Usually the critical dimensions on the drawing, surface finish and any visible defects — enough to prove the setup is right, not a full report. If the part fails, the setup or offset is corrected and another first piece is made and checked; the batch starts only after one passes. A simple record keeps it traceable:

  • Part / program

    Example (illustrative)
    Flange 40-112, O1234
  • Reason for check

    Example (illustrative)
    New setup
  • Dimensions checked

    Example (illustrative)
    Bore Ø40 H7, OD Ø112, face runout
  • Result

    Example (illustrative)
    Bore +0.02 over — offset corrected, second piece OK
  • Approved by / time

    Example (illustrative)
    QC, 10:42

First-piece vs first article inspection

The two are often mixed up. First-piece inspection is routine and repeats after every setup. First article inspection (FAI) is a formal, documented check of every drawing requirement, usually done once for a new part or a design change and often sent to the customer.

Counting the time it takes

The inspection itself may take five minutes; the wait for someone to do it can take much longer. If that time is lumped into “idle”, nobody sees it. If it is recorded as its own planned stop, the real cost of approval per setup becomes visible — and so do the shifts where the machine sat waiting for quality.

ThingConnect includes first-piece inspection as a default stop reason, treated as a planned stop, so operators can tag that wait at the machine. It then shows up as its own line in the downtime report, separate from breakdowns and from setup time.

Frequently asked questions

Usually someone from quality, but many shops let a trained setter approve routine repeat jobs with a checklist and gauges at the machine, keeping quality sign-off for new parts, critical features and any first piece that failed. Faster approval means the machine waits less after each setup.

Only if it passed and will ship. A first piece that is cut up for measurement, kept as a sample or scrapped should be recorded as a setup piece or a reject — otherwise the part count and plan attainment look better than the real output.

Related terms

Filed under

Quality metrics

Live demo

See ThingConnect on a real shop floor

A one-on-one walkthrough with our team.

Book a demo
Talk to our team

See how long setups and first-piece approval really take, machine by machine