Idle time is time a machine is available and planned to run, but isn’t making parts — it is waiting, not broken.

Updated November 20263 min read

← All glossary terms

Idle time is the quiet loss. Nothing is broken and no alarm is sounding — the machine is just standing still during time it was supposed to be running.

What idle time usually is

On a CNC floor, the common causes are ordinary ones:

  • Waiting for material, blanks or the previous operation
  • Waiting for an operator who is running another machine
  • Waiting for first-off inspection or a quality decision
  • Waiting for a program, tool or fixture
  • Setup between jobs, when it isn’t tracked separately

Every one of these looks the same from the machine’s side. That is why idle time only becomes useful once each stop has a reason.

A worked example

One machine, one 8-hour shift (illustrative numbers):

  • Planned production time (8 h minus a 30 min break)

    Minutes
    450
  • Running (in cycle)

    Minutes
    300
  • Handling between parts

    Minutes
    60
  • Stopped by alarms

    Minutes
    25

Idle time = 450 − 300 − 60 − 25 = 65 minutes. Without the handling and alarm split, the same shift would show 150 minutes of “not running” — more than twice the real idle loss, and no clue which part of it to act on.

Idle time vs handling time

ThingConnect puts every moment of a machine’s day into one state, in this order: running, then handling (the planned load/unload window after each part), then alarm, then idle. Idle is what’s left — so a normal part change doesn’t inflate it.

A stop with only a non-critical alarm open reads as idle, not alarm, and any idle stop can be classified with a reason. That turns one large idle number into a short list of causes. See downtime tracking.

Frequently asked questions

No. A short gap between parts while an operator unloads is normal, and some waiting is unavoidable. Idle time becomes a problem when it is long, repeated, or has no recorded reason — because then nobody can tell which cause to fix first.

Start with the reasons. Record why each stop happened for a few weeks, then attack the biggest cause first — often material arriving late, one operator covering too many machines, or slow first-off approval. Fixing one recurring cause does more than a general push to keep machines busy.

Related terms

Filed under

Machine time

Live demo

See ThingConnect on a real shop floor

A one-on-one walkthrough with our team.

Book a demo
Talk to our team

See every idle stop as it happens, with the reason attached