Planned production time is the time a machine is scheduled to make parts — the shift, minus planned stops like breaks and scheduled maintenance.

Updated November 20263 min read

← All glossary terms

Every availability and OEE number is a fraction, and planned production time is the bottom of it. Get the base wrong and every number built on it is wrong too.

The formula

Planned production time = Shift time − Planned stops. Planned stops are the ones decided in advance: meal and tea breaks, scheduled maintenance, meetings, and periods with no orders.

Unplanned stops — breakdowns, waiting for material, setup overruns — stay inside planned production time. They are the losses OEE exists to show.

A worked example

One machine, one shift (illustrative numbers):

  • Shift length

    Minutes
    480
  • Lunch break

    Minutes
    − 30
  • Two tea breaks

    Minutes
    − 20
  • Planned production time

    Minutes
    430
  • Actual running time

    Minutes
    344

Availability = 344 ÷ 430 = 80%. Measured against the full 480-minute shift it would read 72% — a machine blamed for breaks it was never meant to run through. Try it in the availability calculator.

Getting the base right

The common mistake runs the other way: calling more and more stops “planned” until availability looks healthy. If it wasn’t decided before the shift started, it isn’t a planned stop.

ThingConnect takes planned stops from the shift setup, so a scheduled break isn’t counted as lost time, and a shift’s parts target holds flat through lunch instead of running ahead of the machine. Everything else stays in the base, where it belongs. More in the OEE guide.

Frequently asked questions

Usually yes. Setup happens during time the machine is expected to be productive, so it stays inside planned production time and counts as an availability loss. Removing setup from the base would make availability look better without anything on the floor improving.

Start from calendar time and subtract only what is decided in advance: breaks when the machine actually stops for them, scheduled maintenance and planned shutdowns. Where a relief operator keeps a machine running through breaks, the break is not a planned stop for that machine.

Related terms

Filed under

Productivity metrics

Live demo

See ThingConnect on a real shop floor

A one-on-one walkthrough with our team.

Book a demo
Talk to our team

See availability measured against your real shift plan, breaks included